What “finishing” covers, and why it is the biggest stage

Finishing is the plastering, with the wiring and plumbing laid into the walls first, plus the septic tank, doors, windows, ceilings, tiles and first coats of paint. It is usually the biggest stage because it brings in the most trades and materials, and the finish you choose changes it most.

For a three-bedroom bungalow with mid-range finishes, away from Lagos, Abuja and Port Harcourt, finishing is ₦29.6 million to ₦34.5 million and handover ₦12.6 million to ₦14.7 million, on 16 November 2026 prices.

What the finishing stage includes

In our quotes, finishing is the fourth of five stages. It starts once you have seen the roof on, and it turns a closed shell into rooms:

  • wiring and plumbing laid into the walls, then the walls plastered;
  • the septic tank;
  • doors and windows;
  • ceilings, which are PVC panels or POP (plaster of Paris) depending on the finish level;
  • tiles;
  • the first coats of paint.

This is also the last easy moment to run conduits for solar (ZuraLink Power), cameras (ZuraLink Secure), smart switches (ZuraLink Home) and Starlink, because once the plaster is on, every new cable means cutting a wall.

What handover adds

Many people say “finishing” for everything after the roof. In our quotes that work is split in two, and the second part is handover. It brings the kitchen cabinets and wardrobes, the bathroom fittings and light fittings, and the water tank; then the final paint, cleaning and testing; and last, a walk through the snag list with you before the keys. It is invoiced before the fittings go in.

Taken together, finishing and handover for the same bungalow come to ₦42.2 million to ₦49.2 million. That is the figure to hold up when someone quotes you for “finishing” a house. The cost of finishing a house page shows the pair for other houses.

Why it is the biggest stage

Three things make finishing large. It brings in more trades than any other stage: plastering, electrical work, plumbing, carpentry, tiling and painting all happen in it. It reaches every room and every wall. And it holds most of what changes between finish levels, so a better finish lands mainly here.

The figures show it. In the three-bedroom bungalow, walls and structure cost ₦10.2 million to ₦11.9 million whichever finish you choose, yet finishing and handover travel a long way between levels:

  • Standard finish: finishing ₦21.4 million to ₦25 million, then handover ₦7.3 million to ₦8.5 million.
  • Mid-range finish: finishing ₦29.6 million to ₦34.5 million, then handover ₦12.6 million to ₦14.7 million.
  • Premium finish: finishing ₦42.3 million to ₦49.4 million, then handover ₦21.7 million to ₦25.3 million.

When the walls cost more than the finishing

Once a house has an upper floor, walls and structure must also carry the slabs and the stairs. At a standard finish that can push it past finishing: for a 4-bedroom duplex, the structure takes ₦43.8 million to ₦51.1 million while finishing takes ₦38.3 million to ₦44.7 million. Move up to mid-range and finishing takes the lead again, at ₦53 million to ₦61.8 million.

Finishing a house that stopped at the roof

If your house already has its roof on, finishing and handover are all that is left. We inspect what is standing first and price only those remaining stages. For the three-bedroom bungalow at mid-range, that comes to ₦44.2 million to ₦51.6 million. See how to finish an uncompleted house.

Questions and answers

Is painting part of finishing?

Partly. The first coats go on during finishing; the final coat is part of handover.

Is the kitchen part of finishing?

Not in our stages. Kitchen cabinets and wardrobes come at handover, along with the bathroom and light fittings.

Does finishing include furniture or air conditioners?

No. Furniture, appliances and air conditioners are outside every figure. So are solar, CCTV, smart home and internet, which each have their own ZuraLink line.

Why does a premium finish raise this stage so much?

Because nearly everything in it moves up a level: designed POP ceilings, large tiles, and premium doors and windows. See standard, mid-range or premium finish for the full list.

Where to go next

See what your building will cost, stage by stage.

Guide ranges at prices on 16 November 2026. Then ask for one written quote, paid in stages.