The five stages of building a house in Nigeria
A house goes up in five stages: the foundation, the walls and structure, the roof, finishing, and handover. Each one ends at a point you can see and check, which is why we invoice and report one stage at a time.
Put together, the five stages of a mid-range 3-bedroom bungalow in a city such as Ibadan or Enugu add up to ₦75.7 million to ₦88.3 million, using market prices on 16 November 2026.
Foundation: from setting out to the floor slab
The first stage puts the house on the ground. Its outline is marked out on the plot, trenches are dug along it and the concrete footing is cast in them. Blocks are then laid up to floor level, which many builders call DPC level, and over them goes the ground floor slab; some people call this slab the German floor. Any pipes and conduits that must pass under the floor are laid before the slab goes down.
We invoice this stage before we break ground. For the bungalow above it is ₦16.2 million to ₦18.9 million. Wet or sand-filled ground raises it; building on waterlogged land shows by how much.
Walls and structure: the house takes shape
Next the house rises. The block walls go up together with the columns, the lintels are cast (a lintel is the concrete beam over a door or window), and every door and window opening is formed. In a storey building this stage also takes in the upper floor slabs, which most people call decking, and the stairs.
You get this invoice after you have looked over the finished foundation. For the bungalow it comes to ₦10.2 million to ₦11.9 million. A 4-bedroom duplex at mid-range, with an upper floor and a staircase to build, needs ₦43.8 million to ₦51.1 million here.
Roof: closing the building
The roof timber goes up, the covering is fixed on it, and fascia boards are nailed along the edges to close them off. With that done the building is shut against rain, ready for the work inside.
You see the walls before this invoice is sent. The roof is one of the smaller stages, but the finish level moves it: ₦7.1 million to ₦8.3 million for the bungalow under the thicker long-span sheets of a mid-range finish, and ₦12.9 million to ₦15.1 million under the stone-coated roof that comes with premium.
Finishing: from shell to rooms
Finishing is where the bare shell becomes a set of rooms. Wiring and plumbing are laid into the walls and the walls are plastered over them; the septic tank is built; doors, windows, ceilings and tiles go in; and the first coats of paint go on.
Once you have seen the roof on, this invoice follows, and in most houses it is the biggest of the five: ₦29.6 million to ₦34.5 million for our bungalow. Your choice of finish changes it more than it changes any other stage. What finishing covers goes through it in more detail.
Handover: fittings, checks and keys
The last stage fits out the house and gives it to you. Kitchen cabinets and wardrobes are installed, along with the bathroom fittings and the light fittings; the water tank is put in; the last paint goes on; then the whole house is cleaned and everything is tested. Finally we go round the snag list with you, the small faults still to put right, and you receive the keys.
Handover is invoiced before the fittings go in. For the bungalow it is ₦12.6 million to ₦14.7 million.
The same stages in a duplex or block of flats
Every building passes through the same five stages, but the weight shifts as it gets taller. Walls and structure grow, because they now carry the upper floor slabs and the stairs, while the roof covers only the footprint and not each floor. In a block of four two-bedroom flats at mid-range, the walls and structure stage is ₦66.2 million to ₦77.2 million and the roof just ₦10.4 million to ₦12.1 million.
Set the 3-bedroom bungalow beside the 4-bedroom duplex or a block of flats and the pattern is easy to see.
Cables to plan before the plaster
Anything that runs inside a wall is easiest to put in before the plastering. If you want solar and an inverter, cameras and an intercom, smart switches and curtains, or Starlink, ask for the conduits and wiring to be built in as the house goes up. The equipment itself is priced by its own ZuraLink line: ZuraLink Power, ZuraLink Secure, ZuraLink Home, and ZuraLink Connect for Starlink. There is more on smart-ready buildings.
Questions and answers
Which stage of building a house costs the most?
Finishing, in most houses. With a mid-range or premium finish it is the largest stage in every house in our calculator. At a standard finish, a duplex or block of flats can spend more on walls and structure, because of its upper floors and stairs.
Do I pay for all five stages at the start?
No. Each stage gets its own invoice before its work begins, and you see it done before the following one arrives. See how paying in stages works.
What does building up to DPC mean?
It means blockwork laid up to floor level, ready for the ground floor slab. In our quotes that is part of the foundation stage.
Is the septic tank part of the foundation stage?
No. We put it under finishing, with the plastering, doors, windows, ceilings and tiles.
My house stopped at the roof. Can you continue from there?
Yes. We inspect what is standing and price only the stages that are left, which here means finishing and handover. See how to finish an uncompleted house.
Where to go next
- Building cost calculatorYour building, stage by stage
- Cost of building a house in NigeriaEvery reference building and place
- Cost of a foundationFirm and waterlogged land
- Cost of roofingThe roof stage for each building
- Paying in stagesGuide
- What finishing coversGuide
- All guidesPlain answers about building